EPRR Track Plan
Track Work Progress
Click image for larger picture
Feb 4, 2012
Next section ready

Jan 25, 2012
Oops...


Jan 25, 2012
Next bridge section ready



New heavy trucks put to work


Jan 21, 2012
Bottom of 1st tower set


Next span being built

Jan 7, 2012
Moving bottom half of 1st tower.










Feb newsletter will have more coverage.

Thru Dec 30, 2011
Rail out on 3rd span

View from current end








Laager Wye Cut

Thru Dec 17, 2011
Temporary track laid from Monteagle Ind. to bridge bottom.



Moving 16' tall steel bent







Thru Dec 3, 2011
2nd span added



View from west slope

Wye dig into rock

Thru Nov 12, 2011
Bents for bridge



View from Monteagle

First span set





Nov 5, 2011
Wye dig hits rock

Bridge started


Oct 26,2011
Wye tail close to halfway dug

Track now ends at EP&N interchange point


Red Line marks 25' height of next bridge.





Oct 13,2011
Laager wye and abutment for large bridge.



Sep 30,2011
Threshold for Depot train storage

Sep 9-10,2011
Some days the rain come quick

Signal Dept. catching up with track laying.


New Dwarf Signal coming out of Rocky Top Siding

Turnout for Sanders Crossing Bridge



Abutment for bridge,
wye in background

Another siding off Moose Ridge Branch




Abandoned abutment to become Dog Town Mine.

Repair Work at unloading area

Temporary repair

Sep 2, 2011
Laager wye work



New bridge abutment site

Aug 24, 2011
Signals for observation siding

Thru Aug 16, 2011
Rocky Top siding complete


Arriving at Sanders Crossing & Coalmont




Tree across Falcon Gap

Boberg Train Storage

Thru Aug 6, 2011
Rocky Top passing siding almost complete



Thru Jul 30, 2011








Thru Jul 20, 2011












Thru Jul 17, 2011



Thru Jul 2, 2011
New siding extended to first turnout into storage building.


Thru June 24, 2011

40' more to be added


Another close call

New siding off Moose Ridge


Member 4-tk storage

Engineer's new view from loop

June 4, 2011
Signal Dept. off to work

Ties for deck bridge

Roadbed and drainage work for Depot rear track






Up to June 3, 2011
Eagle Gap Bridge progress, 1/3 across.







May 14, 2011
Found two more trees down blocking tracks


May 7, 2011
Track extended to next bridge







April 14, 2011
New ballast car used



April 9, 2011
Tracy City Loop Completed