The CSME Roundhouse Progress Photos

Project foreman: Hank Roberts

Most current work at top.


26 Apr
Turntable pit ready.

17 April
Leveling for tracks and
turntable pit. Trim painting.
9 Apr
Shingling work completed
8 Apr
Shingles for rear roof
Photos from Glenn Johnson
25 Mar
Last of siding added
25 Feb 2008
Siding started
from Glenn Johnson
16 Feb 2008
Leveling back area
from Steve Wassell & Glenn Johnson

Glenn Johnson

Glenn Johnson

Glenn Johnson

Glenn Johnson

Glenn Johnson

Steve Wassell

Steve Wassell

Steve Wassell
12 Feb 2008
Roof covered
before rain came.
9 Feb 2008
Roof sheeting started
15 Jan 2008
Roof framing completed
12 Jan 2008
A little more progress
Rafters started
Dec 29
Rafter cross member
being lifted into place.
Dec 11
Rafters being added
Nov 29
Making walls ready for siding
Nov 27
Wall Framing Work
Nov 18-26
Wall Framing Work
Nov 17
Utility lines laid, backfilling started.
Photos by Dan Davis

More Nov 17 Photos
By Peggy Warren
Nov 1
Finishing block work
Oct 28
Block work on walls starts.
Photos from Peggy Warren
Leftover makes shop ramp and step.
Oct 11, 2007
Floor Poured with excess to shop.
Sep 25, 2007
Digging footers
Oct 1, 2007
More footer work