The CSME Depot Progress Photos

Construction Manager: Howard Warren

Most current work at top.


Through July 27
Doors and siding being added
Through July 23
Work through Jul 15
Trim painting
Interior shots
looking at north wall
and south wall.
Jul 2-3
Added rear roof & windows
drain work

by Peggy Warren

by Peggy Warren

by Peggy Warren
June 26
Drain line(s) work
June 19
Started adding windows
Heat and rain hampered
progress a great deal.
June 6-15
Front roof added
June 5
Ready for front roof
May 15-22
More roof work
May 10-14
Roof work continues
May 6
Rest of roof truss work erected.
May 4, 2010
Roof truss work starts.
(photos by Larry Taylor)
Thru April 22
Outer walls framed

View from front window
Thru April 11
Two outer walls framed
April 3
Floor deck completed
Week of Mar 14
Floor started
Mar 6
Basement walls and
septic tank work
Dec 21
Progress by end of the year
As can be told by photos,
weather has been the big delay
Nov 24
Foundation work complete
photos by Larry Taylor
Nov 21
photos by
Larry Taylor & Dan Davis
Nov 20
photos by
Larry Taylor
Oct 30
Digging septic tank
Nov 2
Current progress
Sept 12
Block work completed
Sep 4
Block work ½ done
Aug 30
Still moving block
Aug. 26
Block arrives
Aug. 10
Footers poured
25 July
Rebar for footers
9 June 2009
Footers dug
And of course
it rained the next day.
9 Oct. 2008
Man vs. stump
Stump won,
will try again later...
3-5 Oct
Digging continues
27 Sep
Digging 50% completed
20 Sep
The digging starts
28-30 Aug
Site clearing completed and
structure laid out.
15-19 July 2008
Clearing building site started
5 Aug
Deborah still working
on clearing trees.